Factory to site
The building is planned.
So is the journey.
Component dimensions, packing, routes, receiving areas, lifting and assembly are reviewed as one delivery system. Logistics feasibility is a project decision that must be resolved before manufacturing and dispatch release.

The principle
Logistics belongs in the design.
A factory-prepared building only works when its components can be transported, received and installed safely at the intended site. The delivery review therefore connects the component schedule with the route, vehicle configuration, crane arrangement, receiving space and installation sequence.
The project plan must establish feasible delivery arrangements before components are released for manufacture. Before dispatch, the contractor and ARTSTONE confirm that the approved receiving conditions and structural interfaces are ready.
Truck type, crane capacity, component weight and delivery timing are determined for the actual project. They are not assumed from an architectural image or a generic building package.
Different products. Different handling plans.
The delivery method follows the component.
| Component family | Transport and protection review | Site handling review |
|---|---|---|
| Fully Integrated Customized Walls | Review each wall’s dimensions, weight, support positions and fitted items. Use engineered racks, restraints and compatible surface / edge protection. | Confirm lifting points, receiving space, temporary support, openings and the sequence for installation and service completion. |
| Architecturally Finished Interlocking Wall Blocks | Plan grouped loads and suitable packing or supports for the block geometry. Protect architectural faces and interlocking projections against handling damage. | Agree unloading, protected storage, movement to the work front and assembly order. Handle blocks according to the approved product and site method. |
| Columns, beams, slabs and stairs | Review component length, geometry, weight, approved support points and lifting provisions. Determine the vehicle and restraint arrangement from the load schedule. | Coordinate crane selection, working positions, structural interfaces and the engineered erection sequence. |
Before production
A project-specific logistics brief.
| Planning input | What it resolves |
|---|---|
| Component schedule | Identification, dimensions, weights, centre of gravity where relevant, support points and approved lifting provisions. |
| Site and route information | Delivery address, approach roads, access points, route constraints and local restrictions requiring review. |
| Transport configuration | Vehicle dimensions, load arrangement, restraints, permissible transport conditions and any required permissions. |
| Receiving and lifting plan | Unloading area, crane position, lifting requirements, ground and support conditions, temporary storage and safe movement. |
| Construction sequence | Which components are needed first, available work fronts and dependencies between deliveries and installation. |
| Responsibilities and conditions | Who coordinates permits, site readiness, equipment, receiving records, damage review and changes to the plan. |
Route feasibility
The complete route, including the last approach.
The review must cover the journey from the factory to the receiving point, including the final access road and site entrance. Vehicle dimensions, turning space, road conditions, load restrictions, overhead clearances and delivery-time restrictions are considered together.
The contractor supplies site information and coordinates access and readiness. ARTSTONE reviews transport and handling for its package. Necessary permissions and transport arrangements are allocated in the project agreement.
Delivery slots are coordinated to limit unnecessary truck queuing. Pedestrian separation, traffic marshals and an agreed unloading / lifting zone form part of the receiving arrangement.

Restricted access
Resolve constraints before committing the component.
Where an access route, unloading area or crane arrangement cannot accommodate the proposed component, the project must review an alternative before production release. That may involve a revised component layout, smaller approved units, a different delivery arrangement or a different receiving and lifting position.
Any change to structural elements, joints or lifting provisions requires the appropriate engineering review. Additional handling or temporary storage must also be included in the protection and handling plan.
The project proceeds to release only when the agreed transport and installation arrangement is feasible. Site constraints can affect scope, cost, equipment selection and programme; those implications are recorded in the revised project offer.
Packing and protection
A protected surface and a supported load.
Architectural surfaces, edges, openings and fitted doors or windows require a defined protection strategy. Branded kraft-paper covering, fibre separators and cardboard edge guards are proposed for compatible finishes, with attachment, moisture behaviour and clean removal validated on actual samples.
Engineered racks and restraints support components at the approved positions. The load plan considers component geometry, support, stability and the receiving sequence. Surface protection and structural load restraint serve different purposes.
Component IDs and drawing revisions are checked against the load manifest. The manifest connects factory inspection, dispatch, site receipt and the installation plan.

Sequence and receiving
Deliver to the work front.
The delivery plan connects truck loads to the approved assembly order. Components are dispatched to match available work fronts and the agreed receiving capacity. Where temporary storage is required, its location, supports, protection and access must be planned.
On receipt, the team checks component identity, revision and visible condition against the delivery records. Discrepancies or damage are recorded for review. Components requiring assessment are held from installation until the appropriate decision is made.
Acceptance, damage review, repair or replacement arrangements, insurance / risk allocation and commercial responsibilities are addressed in the project agreement.
Lift and install
The plan continues after unloading.
Before a lift, the qualified team confirms the component, approved lifting provisions, equipment, access, lifting zone and required temporary supports. Crane arrangements and site conditions must match the engineered installation plan.
After placement, alignment and approved connections are checked. Temporary support and lifting support are released according to the approved method, after the necessary connection and stability checks.
ARTSTONE completes the agreed joints, seals, service connections and local finishes. Protection is maintained while other work continues, then removed within the approved limits for final cleaning and acceptance.

Shared release points
Checks that hold the plan together.
| Release point | Required confirmation |
|---|---|
| Before manufacture | Component design and production information are approved; a feasible transport and installation arrangement is established. |
| Before loading | Components and records are accepted for dispatch; the load arrangement, protection, identity and sequence are checked. |
| Before dispatch | Site access, receiving area, structural interfaces and the planned delivery / lifting arrangements are confirmed. |
| On arrival | The delivery record, component IDs, revisions and condition are checked. Discrepancies are recorded. |
| Before installation | The work front, lifting provisions, equipment and temporary support arrangements match the approved plan. |
| Before completion | Connections and agreed services are inspected or tested; protection, defects, as-built information and handover records are addressed. |
Responsibility matrix
Who coordinates what.
| Activity | ARTSTONE | Registered contractor / project team |
|---|---|---|
| Component and handling information | Develop component details, identity, packing, transport and assembly requirements for ARTSTONE’s scope. | Provide site information and coordinate structural / foundation interfaces with the project engineer. |
| Route and access planning | Review the transport arrangement for the defined components. | Confirm local access conditions and coordinate the agreed permissions and site interfaces. |
| Receiving and work fronts | Confirm requirements for unloading, handling and installation. | Prepare and release the agreed receiving area, access and work fronts. |
| Installation | Supervise ARTSTONE’s installation team and follow the engineered method. | Coordinate other site activities and supervise contractor works. |
| Changes and completion | Assess implications for the package and provide records and tests for ARTSTONE’s scope. | Obtain client approval for agreed changes and coordinate statutory completion. |
Final responsibility for equipment, permissions, temporary works, insurance, damage and interfaces follows the signed project agreement. Each party remains responsible for the work it executes.